Work on Mukkola-Karode NH-66 bypass to begin in two days: NHAI

Contractor got stay order from HC for the stop memo issued on the project by geology dept

Published: 29th December 2022 06:25 AM  |   Last Updated: 29th December 2022 06:25 AM   |  A+A-

Express News Service

THIRUVANANTHAPURAM: The work on the 16.3km Mukkola-Karode NH-66 bypass is set to resume this week as L&T Constructions, the contractor, has obtained a stay order from the High Court for the stop memo issued on the project by the Geology and Mining Department. The memo was issued stating that the contractor excavated soil from an area under the buffer zone to carry out the construction work.

National Highways Authority of India (NHAI) officials said the work would begin in two days, and as decided earlier, the entire stretch will be ready for commissioning by the end of January.

The geology department issued the stop memo by November end against the remaining work at Thangavila. The department alleged the contractor excavated soil from an area under the buffer zone instead of using the allocated land for the purpose in Perumkadavila panchayat near Neyyattinkara. The work hit a roadblock at a time when 98% of the construction was over.

However, the contractor secured a favourable verdict from the High Court on Friday. The court has asked the geology department and the Perumkadavila panchayat to issue a transit pass to the petitioner for quarrying and transporting ordinary earth from the permissible area to the work site.

“Since our two-week work schedule is affected, we will try our best to complete the remaining work in the stipulated time frame. We expect to open the highway in January,” said P Pradeep, project director.

Currently, the work is pending in three locations: Thengavila, Thirupuram, and Vlathankara. Once completed, the stretch will be the first concrete-laid highway in the state. Though the work began in 2016, the NHAI had to push the deadline multiple times owing to several hurdles.

Though the work on the Tamil Nadu side of the NH will not be completed soon due to land acquisition issues, traffic from Mukkola to Karode will be opened once the stretch is completed.

Karode-Kanyakumari   stretch: Tender called  
The NHAI has invited a new tender for the remaining work on the Karode-Kanyakumari stretch in Tamil Nadu. The work is expected to start by April.


India Matters

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.