Mineral Resources and Energy Minister Gwede Mantashe will on Thursday sign project agreements with 13 preferred bidders from round five of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP).
According to an advisory from the Department of Mineral Resources and Energy, these projects will add 975MW to the grid. Mantashe will also make announcements on Bid Window 6 of the REIPPPP.
Among the projects is that of Engie SA. The French developer plans to sign power-purchase agreements for a total of 22MW of solar projects after being selected as a preferred bidder as part of the so-called fifth bid window, according to Mohamed Hoosen, Engie's managing director for renewables in Africa, Middle East and Asia.
South Africa picked 25 wind- and solar-power projects to be built by private developers last year to reduce the nation's reliance on coal for electricity and end rolling blackouts that are curbing economic growth. Those plans have faced various delays and challenges to reach financial close.
"It's always a challenge - the market has changed fundamentally to how it was 18 months ago," Hoosen said in an interview, referring to factors including a surge in supply-chain costs.
South Africa revised commercial close timelines for the projects chosen in the fifth bid window. It's since signed some agreements in a staggered order. Developers also await the selection of preferred bidders for the sixth bid window.
Engie remains interested in realising more projects through the government programme, Hoosen said. "To the extent that they bring these programmes to market, we will be there to submit our bids."
As part of South Africa's energy transition, about 53GW of wind and solar plants will be required over the next decade as ageing coal stations, currently producing over 80% of the nation’s electricity, are retired, according to state-owned utility Eskom.
Job creation
Plans to switch from a dependence on coal mean South Africa, with one of the worst unemployment rates in the world, needs to replace jobs that will be eliminated. A proposed solution is building or assembling some of the equipment in the country.
"There is tremendous value in establishing a local base for manufacturing," though there are some preliminary conditions, Hoosen said. "You need the certainty and reliability of the deployment of renewables" and you need to be competitive.
Engie has about 320MW of renewable projects operating in South Africa, including two concentrated solar power stations capable of storing electricity for hours. That's giving way to the use of photovoltaic panels with batteries "as we look at the evolution of technology and cost", Hoosen said.