BDA to go in for third round of tendering for Dr K Shivarama Karanth Layout

The nine packages which will individually cover the nine sectors in the layout had been totally tendered for a cost of Rs 2,475 crore on October 11.

Published: 16th November 2022 05:42 PM  |   Last Updated: 16th November 2022 05:42 PM   |  A+A-

Dr K Shivarama Karanth Layout

File pic of Dr K Shivarama Karanth Layout when encroachments were cleared. (EPS)

Express News Service

BENGALURU: Five out of the nine packages to create civic utilities in the Bangalore Development Authority's upcoming Dr K Shivarama Karanth Layout will go in for a third round of tendering shortly as only single bidders have made the cut in the technical round of the tendering process. The total cost of these five packages works out to nearly Rs 1233 crore.

A top BDA source said, "Single bids can be accepted only under exceptional circumstances. Hence, these five packages, Package, 1, 3, 4, 5 and 6 will now be retendered."

The nine packages which will individually cover the nine sectors in the layout had been totally tendered for a cost of Rs 2,475 crore on October 11.

These are the approximate costs of the packages that will be retendered: Rs 267.77 crore (P1); Rs 224.79 crore (P3); Rs 212.16 crore (P4), Rs 273.62 crore (P5) and Rs 254.65 crore (P6).

The formation of sites, construction of roads, roadside drains, cross drainage works, stormwater drains, rainwater harvesting, protection works including water supply, UGD and electrical works are covered in each of the packages.

The source said, "There was more than one bid for them actually when they were first opened. One package had two and another even had three bids. However, due to non-submission of required technical documents, their bids were rejected in the technical round. Hence, we will go for the third round for these sectors."

"In the case of the other four packages, the firms that have cleared the technical round will have to clear the financial round next. The process is on and will be completed in a week's time," the source said.

The first round of tendering was done on March 22 this year and it got poor response. The second tender was called for on October 11 and the third one is now set to follow.

The Supreme Court had initially ordered the completion of the tendering process by September end and this could not be met and an extension was sought by BDA. It also asked the Justice AV Chandrashekhar Committee to supervise the layout formation.

The formation of the Layout at a revised cost of Rs 5337 crore was approved by the State government in July this year. The layout will be BDA's second biggest, and 28000 sites will be readied on 3546 acres and 12 guntas. It will extend across 17 villages, between Doddaballapur and Hesaraghatta in North Bengaluru.


India Matters

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.