SA needs R500 billion to end load shedding, says Intellidex

accreditation
Share
0:00
play article
Subscribers can listen to this article
Photo: Getty Images
Photo: Getty Images


South Africa will require R500 billion in private investment to end power cuts that are stalling economic growth by the start of 2025, said Peter Attard Montalto, Intellidex’s head of capital markets research. 

The money is needed to construct 15 gigawatts of generation capacity and five gigawatts of battery storage, he said, adding that the requirement is unlikely to be met within such a tight time-frame. 

South Africa is facing its worst-year yet of power cuts as Eskom Holdings SOC Ltd., the national utility, imposes rolling blackouts, known locally as load-shedding, because is poorly maintained, coal-fired plants keep breaking down. The country has been plagued by outages since 2008.

“Ending load-shedding by end-2024 is possible, but a stretch,” Montalto said in a response to questions. It would require that all efforts to end the crisis and introduce energy reforms “would have to go like clockwork,” he said. 

The country will need to invest an additional 175 billion rand in expanding its power grid over the next decade, Montalto said in a presentation to the Presidential Climate Change Coordinating Commission on Thursday.

We live in a world where facts and fiction get blurred
In times of uncertainty you need journalism you can trust. For 14 free days, you can have access to a world of in-depth analyses, investigative journalism, top opinions and a range of features. Journalism strengthens democracy. Invest in the future today. Thereafter you will be billed R75 per month. You can cancel anytime and if you cancel within 14 days you won't be billed. 