First Metro pier comes up inside Kempegowda International airport campus

It took a little over three hours for completion.

Published: 04th September 2022 04:40 AM  |   Last Updated: 04th September 2022 04:40 AM   |  A+A-

The first pier being cast on the KIA premises on Saturday, for the last stretch of Metro’s Airport Line

The first pier being cast on the KIA premises on Saturday, for the last stretch of Metro’s Airport Line

Express News Service

BENGALURU: The first Metro pier inside the premises of Kempegowda International Airport was cast on Saturday afternoon marking a significant breakthrough for the final stretch of the Phase 2B line from Yelahanka to the Airport terminal station. A total of 67 piers will dot the 15-km line.

It took a little over three hours to complete. “Work on the line began at 1.35 pm and ended at 3.36 pm,” Colonel Vinod Sasalatti, Deputy Chief Engineer, Airport Line, Package 3, BMRCL, told TNIE. Contractor NCC is executing the work.

“It has taken us four months since we began barricading the portion of the airport to ready the pillars. We had to transplant nearly 200 trees that dotted the line, and shift a water utility line, as well as electrical poles to facilitate the work. We had to get permission from Bangalore International Airport Limited at every stage as it passes via their campus,” Sasalatti said.

A total of 16 cubic metres of concrete, brought from the casting yard of Doddajala were brought in a mixer and poured into a pier shutter to facilitate it. The pier touches a height of 8 metres and has a diameter running to 1.6 metres, the official explained. “The pier will be allowed to settle in this condition for 18 hours,” Sasalatti added.

The pier shutter is a unique piece of equipment where the segments are assembled together at the spot with numerous bolts. The 38.44-km KR Puram to KIA line has been divided into three packages. It will be mostly elevated, with just 900 metres running underground inside the airport terminal.

“The two stations inside the terminal will be built by BIAL. Package 3 is on target to meet the Metro Phase-2 deadline of March 2025,” he added.


India Matters

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.