CAG pulls up Army Ordnance Corp for delay in placing orders, cites cases of 'extra expenditure'

The delays in placing orders and materialisation of supplies in case of critical items was an 'inherent' problem affecting the operational preparedness of the Army, it said.

Published: 19th July 2022 10:41 AM  |   Last Updated: 19th July 2022 10:41 AM   |  A+A-

Indian army commandos practise march during the rehearsals for the upcoming Republic Day parade at the Raisina hills, the government seat of power, in New Delhi. (Photo | AP)

By PTI

NEW DELHI: The Army Ordnance Corps has faced flak from the Comptroller and Auditor General (CAG) for instances of delays-- in some cases up to 301 weeks-- in placing procurement orders and extra expenditure.

The delays in placing orders and materialisation of supplies in case of critical items was an "inherent" problem affecting the operational preparedness of the Army, it said.

"Against the prescribed time frame of 23 weeks in Defence Procurement Manual, delay of 13 to 301 weeks was noticed in certain supply orders. The delays were mainly in obtaining acceptance of necessity and completing the tendering process within the bid validity period," the CAG said.

"Against the supply orders/indents placed on Ordnance Factories, Defence Public Sector Undertakings and other vendors, supply orders valuing more than Rs 700 crore were outstanding beyond the delivery period and awaiting completion for the last one to 19 years," it said in a press release.

The report was tabled in the Lok Sabha on Monday.

The Army Ordnance Corp (AOC) is responsible for providing material and logistics support to the Indian Army during war and peace.

The inventory management functions of AOC primarily involve provisioning, receipt, storage, preservation, accounting, stocktaking and issue of ordnance stores.

The CAG also cited cases of "extra expenditure" due to failure to accept the tender within the prescribed period and procurement at higher rates.

"Failure to accept the tender within the validity period in one case led to the retendering and consequent placement of supply orders at an extra expenditure of Rs 6.75 crore," the CAG said.

"There were instances of rates in central procurements at central depots being higher than their local purchases rates made within the last one to six months resulting in an extra expenditure of Rs 4.36 crore," it said.

The CAG said procurement agencies did not utilise the provision of repeat order/option clause and instead placed fresh supply orders at rates higher than the earlier ones, resulting in an extra expenditure of Rs 3.89 crore.


India Matters

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.