The ongoing repairing of the Jogeshwari Vikroli Link Road Flyover (JVLR) initiated by the Maharashtra State Road Development Corporation (MSRDC) appointed contractor has finished the work before time. Following which the said Flyover will be opened to the traffic fully starting tomorrow from 6am onwards.
MSRDC public relations department official confirmed and said that the JVLR Flyover joint and bearing replacement work was undertaken for which permission for traffic block was taken between May 13 and 24th. However, the said repairing was finished before time.
Relief to commuters, #Mumbai Traffic: JVLR flyover repair finished before time. It will be opened to the traffic from tomorrow 6 Am onwards @fpjindia