Here's The Update On Ahmedabad-Mumbai Bullet Train Project

The 508.17-kilometre long network will pass through Mumbai, Thane, and Palghar in Maharashtra, and Valsad, Navsari, Surat, Bharuch, Vadodara, Anand, Kheda, and Ahmedabad in Gujarat

Photo Credit :

1507547432_Mt57zj_Bullet-Train-st470.jpg
Print this article Font size

Union Minister for Railways Ashwini Vaishnaw on Wednesday shared the current status of Mumbai - Ahmedabad High Speed Rail (MAHSR) Project in the lower house of the Parliament.

Key highlights from the project status report are:

Admitting that the Covid-19 pandemic had an adverse impact on the project, Vaishnav said that the project indeed got delayed. However, he cited some other factors as well for delay in project execution such as land acquisition, especially in the state of Maharashtra and the consequent delays in the finalisation of contracts.

"The cost of MAHSR Project is ₹1,08,000 crore as in 2015. The anticipated increase in cost and time can be fully ascertained only after completion of Land Acquisition, finalisation of all contracts and associated timelines," he added.

The 508.17-kilometre long network will pass through Mumbai, Thane, and Palghar in Maharashtra, and Valsad, Navsari, Surat, Bharuch, Vadodara, Anand, Kheda, and Ahmedabad in Gujarat.