Koch

GCDA slammed for delaying Bund Road development

Kochi, Kerala, 08/02/2022.The GCDA can develop Chilavannur Bund Road if this narrow 250 m portion on Thykoodam side is acquired. Photo by Vibhu H.   | Photo Credit: VIBHU H

Facing the heat over the inordinate delay in acquiring 56 cents at Thykoodam and at Thevara to develop the Chilavannoor Bund Road as a two-lane road, the Greater Cochin Development Authority (GCDA) has decided to revisit the project and set in motion efforts to fast-track the acquisition process, sources in the agency said.

Once developed, the 3.50-km-long road would decongest Vyttila, the arterial SA Road and Pallimukku Jn. on MG Road.

“Eighty per cent of the road was readied over a decade ago. The land (and buildings) near Thykoodam, from where the road takes off, constitutes 10% of the balance land needed. Another 10% land ought to be acquired on the Thevara end, to straighten the road’s alignment and to prevent demolition of a few buildings there.” The landowners, who agreed to surrender their land after resisting the acquisition move for many years, have been given two options – either to accept compensation or to opt for mutual exchange of land. In this, the GCDA would allot them land which has a higher value, at Panampilly Nagar, they added.

Agitation planned

Expressing concern at the GCDA’s decades’-long ‘apathy’ in developing the road, A.X. Sebastian, the Vyttila mandalam president of the Congress said the entire road can be developed for approximately ₹5 crore. “The GCDA did nothing during the past years, although most landowners and those of church-owned property were willing to hand them over to the agency in order to realise the road. A memorandum in this regard was handed over to the new Chairman of GCDA, K. Chandran Pillai, on Monday.”

“The agency must also widen the road’s bell-mouth near the Thykoodam underpass, to enable smooth movement of vehicles. We will wait for a month more, following which a relay agitation will be organised if the road project is not set in motion,” he said.

Stakeholders have also apprised the GCDA of the possibility of hewing out a road parallel to the congested Pandit Karuppan Road, by readying a branch road leading eastward towards Thevara Ferry Road, from K.P. Vallon Road.

  1. Comments will be moderated by The Hindu editorial team.
  2. Comments that are abusive, personal, incendiary or irrelevant cannot be published.
  3. Please write complete sentences. Do not type comments in all capital letters, or in all lower case letters, or using abbreviated text. (example: u cannot substitute for you, d is not 'the', n is not 'and').
  4. We may remove hyperlinks within comments.
  5. Please use a genuine email ID and provide your name, to avoid rejection.

Printable version | Feb 9, 2022 2:36:07 AM | https://www.thehindu.com/news/cities/Kochi/gcda-slammed-for-delaying-bund-road-development/article38399207.ece

Next Story