With no relief in sight despite coal stocks running critically low and production disruptions looming across the Indian aluminium sector, the Aluminium Association of India (AAI) has approached the Ministry of Coal, urging the immediate resumption of adequate coal rakes for the highly power-intensive Aluminium industry.
In its representation to the Ministry, the AAI has lauded the combined efforts by the Ministry of Coal and Coal India Limited in reviving domestic coal production, which has helped ease the coal supply crisis for the Power Sector. The steps undertaken by the Ministry increased the overall daily rakes dispatched from 242 rakes/day in September 2021 to 289 rakes/day in December 2021. This has drastically strengthened the coal stocks of the Power Sector to around 10 days, a marked improvement from a mere 2-3 days in the months of September-October last year.
However, this has come at enormous cost to the Captive Power Plants (CPP)-based industry and the worst impacted is the Indian aluminium industry, which continues to see depleting coal stocks of only 3-4 days, abysmally low compared to the prescribed level of 15 days for the sector. Struggling to cope with this prolonged crisis since the second quarter of this fiscal year, the AAI has now sought the Ministry's support to ensure adequate supplies to the CPPs by earmarking at least 25-30 coal rakes per day to ensure viable industry operations.
The need for the CPPs is especially urgent, given that Aluminium production is a continuous process that requires huge volumes of uninterrupted quality power supply. This quantum can only be met only through the in-house CPPs set up by all the aluminium smelters plants to meet this specific requirement. Accordingly, the industry has established Captive Power Plants of 9,400 MW capacity (comprising 34 per cent of the cumulative thermal CPPs capacity domestically) to supply continuous power for Aluminium operations.
Even though the Government has reiterated that there is now an improved availability of coal in the country overall, the non-availability of rakes for the non-regulated sectors remains a major concern. Curtailing coal supplies to Captive Power Plants (CPPs) has directly resulted in a coal crunch situation for the Aluminium Sector. Any power interruption in an aluminium smelting operation for more than 2 hours can lead to the freezing of molten aluminium within the smelting pots, which takes a minimum of 6 months to fix, and then almost a year to once again begin yielding the desired metal output, causing enormous production, cost and supply disruptions. With the continued crisis, it will take over a year's time to clear the backlog of rakes, and for the CPPs to build and maintain adequate coal stocks for sustainable operations. The crisis further aggravates with the last-minute cancellation of coal auctions for NRS, giving no relief for the domestic industry to secure coal for manufacturing and CPP-based industries.
With the ongoing revival of the economy and increased post-pandemic industrial activity, the CPP-based industries are highly dependent on uninterrupted coal supplies which is vital for sustainable operations and the continued cost-competitiveness of power intensive industries vis-a-vis global players. Any production curtailment by this sector will have cascading effect on consumption and downstream supply chain, thereby adversely impacting the nation's GDP growth.
The AAI representation has gone on to highlight that since August 2021, the Non-Regulated Sector has been facing uncertainties in securing sufficient coal rakes for continued operations, with supplies limited to just 40-50 per cent of the required coal. This has led to a backlog of over 6000 coal rakes as most of the available coal and rakes are being diverted to the Power Sector as "Priority Coal Supplies", even despite their coal inventory situation drastically improving.
--IANS
san/skp/
(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)
Dear Reader,
Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.
We, however, have a request.
As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.
Support quality journalism and subscribe to Business Standard.
Digital Editor
RECOMMENDED FOR YOU