Nine years on, Jakkur rail bridge still hangs fire

Even as commuters to and from Jakkur take a jam-packed, circuitous route of over 5 km to reach Yelahanka Main Road, a rail over bridge (ROB), which began work in 2012, is still in limbo.

Published: 18th August 2021 06:41 AM  |   Last Updated: 18th August 2021 06:41 AM   |  A+A-

Work on the Jakkur Flyover has come to a complete standstill for the last four years 

Express News Service

BENGALURU: Even as commuters to and from Jakkur take a jam-packed, circuitous route of over 5 km to reach Yelahanka Main Road, a rail over bridge (ROB), which began work in 2012, is still in limbo. The half-done work by Railways had to be stopped as BBMP was unable to complete the land acquisition process. The 6,515-sqm land in contention is owned by four families who have taken the BBMP to the High Court over it.

“They insist on a much higher compensation than what has been offered by the government and claim ownership of additional land than what is shown in records,” said a BBMP source.

The cost of the bridge has shot from `13.71 crore to over `25 crore over the years. The Railways and BBMP were supposed to share half the initial cost. “The sudden move to convert the proposed two-lane flyover to a four-lane one on the insistence of the then MLA also required more land and delayed it more,” said another source. “The additional cost incurred was to be borne fully by the BBMP,” he added.

A top railway official said that SWR has completed work in all parts where it was possible to do so. “We have built the bridge above the railway track, two spans on the Approach Road and even the pedestrian underpass here. The precast girders are ready and we can put up four more spans when the land is made available,” he said.

The official said it would take six to eight months to finish the project after the land acquisition is complete.With the matter pending before the court, no one knows when it will be resolved. Among those who have suffered in their daily commute to work is Gayathri, a resident of Nehru Nagar, a software professional at Manyata Tech Park. Explaining her commuting woes, her husband Joshua told TNIE, “If the flyover is readied, she will be able to reach her workplace within 20 minutes. There have been many days (pre-covid) when she travelled nearly an hour via Hebbal and Veeranapalya to reach her office.”


Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.