Three weeks after water release, Odisha's Indravati embankment breached

Though the exact reason behind the breach was yet to be ascertained, locals attributed it to substandard construction of canal embankments and linings.

Published: 01st August 2021 09:56 AM  |   Last Updated: 01st August 2021 09:56 AM   |  A+A-

Breach in Indravati mega lift canal embankment.

Breach in Indravati mega lift canal embankment. (Photo | Express)

By Express News Service

BHAWANIPATNA: Breach in the newly-constructed Indravati Mega Lift canal flooded paddy crops on more than 100 acre of land in Koksara block of the district in the early hours of Saturday.

Sources said, a small breach eventually broke a large portion of the embankment near Majhiguda village, leading to siltation in more than 20 acre of paddy field. The damaged portion was about 10 feet in width. 
Built at a cost of `986.71 crore, the Indravati lift irrigation project was dedicated to the state by Chief Minister Naveen Patnaik on January 14 and water was released in the mega lift canal for the first time for irrigation on July 8.

The incident happened hours before a team of senior officials, led by Chief Secretary Suresh Chandra Mohapatra, reached the district to review development projects. Though exact reason behind the breach was yet to be ascertained, locals attributed it to substandard construction of canal embankments and linings. The canal was in spate following incessant rains that battered the district recently.

A team of revenue officials led by the Koksara tehsildar visited the spot to assess the damage. The officials assured that the affected villagers will be compensated as per rules.  Chief construction engineer of Indravati project Bibhusharan Mishra, executive engineer of lift canal system Kondol Rao, representatives of L&T which executed the project and other officials visited the spot to ascertain the cause of breach.

“We are investigating what could be the possible reasons that led to the breach. As per agreement, the constructing agency will look after the maintenance for five years. The entire stretch of the embankment will be inspected once again,” said Rao. The mega lift project is targeted to benefit 88 villages under Koksara block of Kalahandi by providing irrigation to 25,274 hectare of land during the current kharif season.


Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.