The government has extended relief to the renewable sector amid the second wave of the Covid-19 pandemic by allowing an extension of two-and-a-half months for power projects with commissioning dates between April 1 and June 15, 2021.
The Ministry of New and Renewable Energy (MNRE) has notified the changes that will prevent developers from being charged penalty for delaying commissioning of projects beyond the agreed timelines.
With the second wave of the pandemic resulting in lockdowns in different parts of the country, work on several power projects also got suspended resulting in delays in commissioning.
Last month, MNRE had issued notification allowing renewable projects with commissioning dates on or after April 1, 2021, an extended schedule subject to continuing of existing PPAs and no increase in project cost due to delays.
Even last year during the Covid outbreak and lockdowns, MNRE had given an extension of five months to projects getting commissioned between March 25 and August 24, 2020.
The power ministry has also granted an extension of three months to all interstate transmission projects under construction, with the scheduled commercial operation date (SCOD) falling after April 1, 2021, hit by the resurgence of the Covid-19 pandemic.
Recent Post
Never Miss A Post!
Sign up for free and be the first to
get notified about updates.
Most Popular
How to properly recycle your technology
- Jun 30, 2021
All that you need to know about Business VPNs
- Jun 29, 2021
More Stories
Grow Your Business
All Rights Reserved © 2017 - 2021