Pending smart city works get boost during lockdown

Unlike the first lockdown, the second one was utilised by the government and the city corporation to complete the ongoing Smart City road works.

Published: 16th June 2021 06:53 AM  |   Last Updated: 16th June 2021 06:53 AM   |  A+A-

With some relaxations made to lockdown norms, vehicles seen caught in a traffic jam on NR Road, near Town Hall, in Bengaluru on Monday | VINOD KUMAR T 

Express News Service

BENGALURU: Unlike the first lockdown, the second one was utilised by the government and the city corporation to complete the ongoing Smart City road works. 21 roads have been completed and will be open for commuters in June and July. According to information shared by Bengaluru Smart City Limited (BSCL), work on a total of 15.15 km of road has been completed during the second lockdown and work on 4.843 km is pending. 

The list of roads which will be open for people to use from June-end include, Hayes Road, Wood Street, Tate Lane, Raja Ram Mohan Roy Road, Convent Road, Mcgrath Road, Castle Street, Lavelle Road, Brigade Road, Dickenson Road, Queens Road, Palace Road and Infantry Road. According to officials, by the end of July, the remaining roads — Commercial Street, Cantonment Road, Millers Road Extension, Jumma Masjid Road and Kasturba road will be completed and open in July.

Rajendra Cholan, Managing Director, BSCL told The New Indian Express, in case of most of the roads, the final tarring, closing of ducts and clearing of pavements is pending. If weather permits then the works will be expedited. He said that the lockdown period was utilised to complete the works because traffic movement was minimal.

A total of 31 roads were taken up under the Smart City works in Bengaluru. Of this, 21 are done, he said, adding, the pending are- Kamaraj Road, Avenue Road, Infantry Road, Race Course Road, Ulsoor Road, Raj Bhavan Road and Planetarium Road. 

Cholan said in case of pending works, one side of the works and ducts are done, while pavers and underground cabling are pending. In case of the rest like MG Road, Shivajinagar, Balekundri Circle, Richmond Road, Residency Road and Ali Askar Road work is still going on. 

“The work has been going on with whatever labour strength was available. Unlike before, there were labourers, but there was a shortage. However, the projects are delayed, because many government offices also experienced a setback because of Covid, so clearance of files was slowed down,” a BBMP official said.


Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.