A lotus-shaped landing field: GVK group reveals Navi Mumbai airport design

The airport will be developed in four phases. After the first phase it will be able to handle a minimum of 10 million passengers

Topics
GVK | Navi Mumbai | Mumbai airport

Aneesh Phadnis  |  Mumbai 

Navi Mumbai International Airport
The airport will be developed in four phases. After the first phase, it will be able to handle a minimum of 10 mn passengers

The international airport will boast three interconnect­ed multi-level terminals with a lotus-inspired design, according to the master plan prepared by its outgoing developer.

The group, which completed 15 years of airport business, shared the first look of the airport on Tuesday.

The group in 2018 had comm­iss­ioned British firm Zaha Hadid Architects to design the main terminal and air traffic control tower. The master plan of the airport was approved by the City and Industrial Development Corporation (CIDCO) in 2019.

The airport will be developed in four phases. After the first phase it will be able to handle a minimum of 10 million passengers. According to the master plan, the airport’s main terminal (T1) that will be built in phase one would have two floors with very few level changes and minimum walking distances. The airport would eventually have a passen­ger handling capacity of 90 million per year.

The airport will be built over 1,160 hectares, over 95 per cent of which has been acquired from local villagers. Hill cutting and land filling works are on. The site had a cluster of villages with ponds full of lotuses and that inspired the terminal design.

Last August, the group announced an exit from the airport sector selling its stake in to the Adani group. The actual handover is, however, yet to happen.

According to the concession agreement between CIDCO and GVK, the date of commercial operations of the airport was fixed at this year-end. This would need to be amended. Also, given the changed business environment and sharp fall in traffic last year, the Adani group may review and revisit the construction plans.

Both Adani and groups declined to respond to queries on the matter.






Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.
We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Read our full coverage on GVK
First Published: Wed, June 09 2021. 23:36 IST
RECOMMENDED FOR YOU