NAREDCO requests UP RERA to consider giving extension to real estate projects

NAREDCO requests UP RERA to consider giving extension to real estate projects
By , ET Bureau
Share
Font Size
Save
Comment
Synopsis

According to data by the Ministry of Housing and Urban Affairs, 65,539 cases have been disposed of by the respective state RERA authorities as of 24 April 2021. Out of this, nearly 40% cases (26,510 complaints) were resolved in Uttar Pradesh alone, followed by Haryana with 13,269 cases and Maharashtra with 9,265 cases.

ET Bureau
The National Real Estate Development Council (NAREDCO) for Uttar Pradesh has written to the Real Estate Regulatory Authority (RERA) of the state asking to grant six months automatic time extension for compliance of various orders issued by UPRERA, as construction activities at all real estate projects have come to a complete standstill with the escalation of second wave of COVID-19 cases.

According to data by the Ministry of Housing and Urban Affairs, 65,539 cases have been disposed of by the respective state RERA authorities as of 24 April 2021. Out of this, nearly 40% cases (26,510 complaints) were resolved in Uttar Pradesh alone, followed by Haryana with 13,269 cases and Maharashtra with 9,265 cases.

NAREDCO-UP has also requested state RERA to grant six months automatic time extension of timeline for completion of various projects of developers registered with UP-RERA.

It has also requested for six months time extension for submission of various returns and documents.

“This will give the developers a breathing space to re-organise the construction activities and find resources to comply with various orders of RERA,” said RK Arora, chairman, UP-RERA.

NAREDCO, in its letter has said that persons in large numbers associated with construction activities, have become COVID positive and many have even died.

“Some of the projects have been sealed by the District Administration prohibiting any kind of movement to and from these projects. The second wave of COVID-19 is considered to be a national natural calamity qualifying for force majeure for all purposes and relief measures are being taken by the government on war footing basis,” the letter said.

The situation has brought the construction activities at all projects to a complete standstill as the weekend curfew/lockdown was clamped on from April 23.

“Since the COVID-19 cases are still rising rapidly and no indication of the situation improving visible, it is expected that the construction will suffer at least for next six months. Even after that, it will take time to restore the material supply chain, re-engagement of manpower and machines,” the letter says.

The disruption of construction has also brought the developers to a situation of liquidity crisis as the collections have been completely stopped and the banks and financial institutions are not releasing funds against flats under their home financing arrangement.

Read More News on

(Catch all the Business News, Breaking News Events and Latest News Updates on The Economic Times.)

Download The Economic Times News App to get Daily Market Updates & Live Business News.

ETPrime stories of the day