Polavaram price escalation due to ‘revised scope’

Officials say works worth Rs 799 crore were added to scope due to changes in designs

Published: 28th April 2021 08:34 AM  |   Last Updated: 28th April 2021 08:34 AM   |  A+A-

By Express News Service

VIJAYAWADA: Amid criticism by opposition parties over the revision of Polavaram costs, the state water resources department, which termed the allegations baseless, clarified that changes in the price were largely due to revised scope of works as per revised designs approved by the Central Water Commission. The department prepared a statement showing the difference between administrative approvals given for the head works of Polavaram Irrigation Project and what necessitated the revision of cost.

According to the statement, the government had given administrative sanction for Rs 5,535.45 crore (pre-GST) on September 8, 2016. After reverse tendering, changes in designs and thereby scope of works and other non contractual works, the department issued an order on April 19 this year according administrative sanction for a revised amount of Rs 7,192.02 crore. The officials explained that only Rs 799.15 crore worth additional works were added to the scope due to changes in the designs that too as approved by the dam design review panel/Central Water Commission. 

While the head works estimated value in the recently given order is in fact Rs 268.93 crore lesser than the 2016’s approval (Rs 5,266.52 crore), the officials added that non-estimated contract value items of Rs 919.75 crore were included. 

Even in the Rs 919.75 crore, Rs 515.45 crore is towards GST provision and another Rs 404.27 crore is for works such as construction of a three-floor building for control room, safety and lighting arrangements, sub-stations, land acquisition in dump areas, construction of a model house, ghat road, road improvement from Kovvur to Ramayapet, power charges and others. 

“A probable price escalation of Rs 153.36 crore for Transstroy joint venture and Navayuga Engineering Company Ltd in 2018-19, and another Rs 53.24 crore for deviations approved in works of spill channel, diaphragm wall cut off, protection of cofferdams, executed by NECL in 2018-19, were included in the latest sanction,” a senior official explained.


Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.