"Unit-2 of 660 MW capacity of Nabinagar Super Thermal Power Project (3 x 660 MW) of Nabinagar Power Generating Co. Ltd...has successfully completed trial operation and consequently included in the installed capacity of NTPC Group from March 31, 2021," a BSE filing said.

State-owned NTPC on Thursday said it has commissioned the second unit of 660 MW of the Nabinagar Super Thermal Power Project in Bihar. With this, the total installed capacity of NTPC Group has become 65,150 MW, the power giant said.

"Unit-2 of 660 MW capacity of Nabinagar Super Thermal Power Project (3 x 660 MW) of Nabinagar Power Generating Co. Ltd...has successfully completed trial operation and consequently included in the installed capacity of NTPC Group from March 31, 2021," a BSE filing said.

Nabinagar Power is a wholly-owned subsidiary of NTPC.

Earlier, Nabinagar Power was a 50:50 joint venture between NTPC and Bihar State Power Holding Company.

The first unit of 1980 MW Nabinagar plant was commissioned in July 2019.

Read More News on

(Catch all the Business News, Breaking News Events and Latest News Updates on The Economic Times.)

Download The Economic Times News App to get Daily Market Updates & Live Business News.

ETPrime stories of the day