The State government has claimed that substantial progress has been achieved in the construction of the Polavaram project in the last 19 months in spite of the COVID-19 crisis and the floods in the Godavari in August 2020, and it is poised to be completed by the end of the current calendar year.
According to an official release, the entire concrete work on the spillway pillars and slabs will be completed by the end of February. Of the total 48 radial gates, nine have been erected, and the remaining will be in place by April.
All the 170 spillway bridge concrete girders have been placed in 18 months. The construction of 40 out of 48 spillway bridge slabs have been completed during the period.
Rehabilitation works
According to the release, the construction of over 11,000 houses for the project-displaced families has been completed and rehabilitation of 17,860 families will be done by May. The coffer dam construction will be completed by June.
Chief Minister Y.S. Jagan Mohan Reddy is personally monitoring the project, which will irrigate nearly three lakh hectares in East Godavari, Krishna, Visakhapatnam and West Godavari districts.
It is proposed to supply 23.44 tmcft of water for drinking purpose to several villages around Visakhapatnam and also meet the requirement of the steel plant through the left main canal. The project comprises a hydro power plant of 960 MW capacity (12 units of 80 MW each).
You have reached your limit for free articles this month.
Subscription Benefits Include
Today's Paper
Find mobile-friendly version of articles from the day's newspaper in one easy-to-read list.
Unlimited Access
Enjoy reading as many articles as you wish without any limitations.
Personalised recommendations
A select list of articles that match your interests and tastes.
Faster pages
Move smoothly between articles as our pages load instantly.
Dashboard
A one-stop-shop for seeing the latest updates, and managing your preferences.
Briefing
We brief you on the latest and most important developments, three times a day.
Support Quality Journalism.
*Our Digital Subscription plans do not currently include the e-paper, crossword and print.
A letter from the Editor
Dear subscriber,
Thank you!
Your support for our journalism is invaluable. It’s a support for truth and fairness in journalism. It has helped us keep apace with events and happenings.
The Hindu has always stood for journalism that is in the public interest. At this difficult time, it becomes even more important that we have access to information that has a bearing on our health and well-being, our lives, and livelihoods. As a subscriber, you are not only a beneficiary of our work but also its enabler.
We also reiterate here the promise that our team of reporters, copy editors, fact-checkers, designers, and photographers will deliver quality journalism that stays away from vested interest and political propaganda.
Suresh Nambath