Bullet train will run in Gujarat only if the red signal is found in Mumbai

31

In any case, the central government is now engaged in the exercise of launching the bullet train on the track. If the land acquisition in Mumbai continues to be hampered, then the train will run in Gujarat on the proposed 508 km corridor between Ahmedabad-Mumbai.

The Railway Ministry has made it clear that if the Maharashtra government did not help in land acquisition, the bullet train would not run in two phases. In the first phase, this train can be run on a 325 km track between Ahmedabad to Vapi. Only if the land acquisition is approved will the bullet train run from Vapi to Bandra in the second phase?

Railway Board CEO Vinod Kumar Yadav said that 67 percent of the land has been received for the bullet train project. Of this, 825 hectares of land have been acquired out of 956 hectares in Gujarat. Due to the acquisition of about 90 percent of the land in Gujarat, the groundwork has been started by issuing tenders.

By the way, the Maharashtra government has assured to acquire the land in four months. Out of 432 hectares in Maharashtra, 97 hectares of land has been acquired. This is only 22 percent of the required land. Out of 8 hectares of land in Dadar and Nagar Haveli, seven hectares of land has been acquired.