Gasoil News - Published on Thu, 29 Oct 2020

Equinor announced that surveys of the damage after the fire at Hammerfest LNG on 28 September indicates that the LNG plant will be closed for up to 12 months for repairs. In addition to damage caused by the fire on the air intake on one of the plant's five power turbines, large amounts of seawater from the extinguishing have damaged other auxiliary systems such as electrical equipment and cables in the plant.

It is the scope of work of this consequential damage that are considered the most extensive and the duration of the shutdown will depend on the delivery time of necessary equipment. Progress will also be affected by the current restrictions related to the Covid 19 virus.

Equinor, as well as the PSA and the police have started independent investigations of the fire.