Difficult to meet deadline for desilting lakes: NGT

Labour shortage, rain delay work; agency for disposal not yet decided

Published: 11th October 2020 04:26 AM  |   Last Updated: 12th October 2020 03:27 PM   |  A+A-

A file picture of a frothy Bellandur Lake 

A file picture of a frothy Bellandur Lake 

Express News Service

BENGALURU: The National Green Tribunal (NGT) expert committee has expressed its apprehension over the deadline set by the state government to desilt Bengaluru’s Bellandur and Varthur lakes, which have hit the headlines for froth flow.  The state government had assured the NGT committee that the lakes would be desilted by December 2020, but the latter is not sure of this. The committee, appointed by the tribunal to ensure the two water bodies are revived, says it will be a difficult exercise.

A committee member told TNIE, “Due to the pandemic, shortage of labourers, and the ongoing monsoon, it will be difficult to finish the desilting by December 2020, as the state government officials commit. The silt is being scraped and dumped on the side of the lakes, which is not what they are supposed to do. Scientific disposal of the silt and its management is also a part of the exercise. All the silt mounted on the banks is soiled and mucky. It cannot be transported.”

The member added that engineers from Bangalore Development Authority said they had cleared silt from the 200-acre Bellandur Lake, but with rainwater stagnating on the water body, the exercise will only get worse. “We will inspect the lakes now and submit a report to the NGT on the next course of action.

Test reports of the silt samples are also awaited, based on which the type of treatment to be given and where it is to be sent, will be decided. Though abandoned quarries have been identified for dumping the silt to level the lands, the agency to transport the silt has not yet been finalised,” the committee member added. 

They, however, expressed pleasure over the creation of sewage treatment plants. “Though it is slow, it is progressing. There are positive signs on the setting up of STPs in Agaram, Sarakki, Hulimavu and Chikkabegur. But completion of the 150 MLD STP near the lake sites is still delayed,” they added. 


Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.