17 new STPs to lead to a cleaner Hussainsagar

TSPCB submitted a compliance report to NGT on steps taken by State for treatment of sewage that flows into Musi river

Published: 18th September 2020 09:34 AM  |   Last Updated: 18th September 2020 09:34 AM   |  A+A-

Hussainsagar Lake

The Hussainsagar Lake in Hyderabad (Image courtesy Wikimedia Commons).

By Express News Service

HYDERABAD: The Hyderabad Metropolitan Water Supply and Sewerage Board (HMWS&SB) will construct 17 new Sewage Treatment Plants (STPs) with a combined capacity of 376.5 MLD in Hyderabad in the catchment area of Hussainsagar lake. The constructions have been taken up in order to augment the capacity of sewage treatment in the city and to cut down water pollution due to contamination with untreated sewage water. A Government Order was issued on September 11 in this regard, sanctioning `512.35 crore, which is 40 per cent of the total estimated cost of Rs 1,280.87 crore. The cost is comparatively high as the new STPs are to be constructed in the Hybrid Annuity Model (HAM).

This information was presented by the Telangana State Pollution Control Board (TSPCB) in its compliance report to the National Green Tribunal, on steps taken by the Telangana government for treatment of sewage that flows into the Musi river, in response to a petition on the poor condition of the river.  The TSPCB also submitted in its report that the sewage treatment capacity of each of the three STPs located near KIMS Hospital, Khairatabad and Ranganadhamuni lake would be doubled from 30 MLD to 60 MLD, from 20 MLD to 40 MLD and from 5 MLD to 10 MLD respectively.

Apart from this, the Water Board would also construct, as part of two packages, eight STPs with a combined capacity of 402.5 MLD and six STPs with a capacity of 480.5 MLD.The TSPCB also submitted that until the year 2036, the Water Board plans to construct a total of 62 STPs in Greater Hyderabad limits, with a combined capacity of 2,057 MLD. The current capacity of all functional STPs in Greater Hyderabad stands at 772 MLD. The STPs are part of a ‘Sewerage Master Plan,’ spreading across a length of 2,676.15 km at a cost of `4783.78 crore. As per the TSPCB report, installation of Online Continuous Emission Monitoring Systems (OCEMS) in all existing STPs would be completed by the end of November. The State government has also identified 27 drains along the Musi for taking up phytoremediation.

Comments

Disclaimer : We respect your thoughts and views! But we need to be judicious while moderating your comments. All the comments will be moderated by the newindianexpress.com editorial. Abstain from posting comments that are obscene, defamatory or inflammatory, and do not indulge in personal attacks. Try to avoid outside hyperlinks inside the comment. Help us delete comments that do not follow these guidelines.

The views expressed in comments published on newindianexpress.com are those of the comment writers alone. They do not represent the views or opinions of newindianexpress.com or its staff, nor do they represent the views or opinions of The New Indian Express Group, or any entity of, or affiliated with, The New Indian Express Group. newindianexpress.com reserves the right to take any or all comments down at any time.