Ayodhya: Now we have to wait for the regular excavation of the foundation of Ram temple!

45


The foundation of the grand Ram temple in Ayodhya, Uttar Pradesh, will have to wait longer to be excavated. After the Ram Mandir Construction Committee meeting, Shri Ram Janmabhoomi Tirtha Kshetra Trust General Secretary Champat Rai said that the regular work of digging the foundation for the temple construction will start after 15 October.


The rig machine from Kanpur will test only testing now. In which a pillar one meter wide and 100 feet deep will be tested. Regular excavation work will be started after the test report is received in a month.

At the Ram Janmabhoomi complex, a meeting was held today by L & T officials trust members along with Ram temple construction committee chairman Nripendra Mishra.

Shri Rai said that the construction of the Ram temple will begin in October, under which the foundation will be dug for 1200 pillars. This is technical work. The foundation age of the temple should be more than the stone of the temple. IIT Chennai is doing testing.