Coimbator

Completion of shutter repair works in KRP Dam likely by June

Replacement of shutters under way at KRP Dam in Krishnagiri.   | Photo Credit: N_Bashkaran

Two and half years after the Krishnagiri Reservoir Project (KRP) Dam’s shutter breached spawning concerns over the dam’s structural safety, the replacement of shutters of the dam is gaining momentum here.

The works on the erection of shutters of KRP Dam has sped up, with 5 of the 7 shutters that were taken up for replacement completed. As on Monday, five shutters were already erected in place, and the works on the 6th shutter has commenced.

The dam’s first shutter had breached from corrosion in 2017, and the shutter was replaced a year later under the State funds. The reservoir’s full capacity of 52 feet was lowered after the breach raised concerns on the structural safety of the other shutters. In 2018, the project to replace the remaining shutters was set in motion, under the funds of World Bank under its Dam Rehabilitation and Improvement Projec (DRIP) in place here.

With the works under progress, any Summer showers will not allow storage in the reservoir. The water storage is at crest level with 25 feet, and any inflow above that will be let out.

The erection of shutters 2,3,8, 4 and 7 were completed but miscellaneous works such as welding, blasting, sand blasting, primer works remain. The authorities are hopeful the shutter works would be fully completed by June, a little ahead of the schedule assigned to the contractor. The dam would be ready in time to receive inflow from the monsoons after June.

Why you should pay for quality journalism - Click to know more

Next Story