Polavaram: Andhra\'s lifeline hit by political roadblock

Polavaram: Andhra's lifeline hit by political roadblock

Press Trust of India  |  Visakhapatnam 

The irrigation project, considered the lifeline of resource-starved and a major election issue this time, has suffered a lot due to a long-drawn slanging match between the Centre and the state government, say officials.

The project is expected to irrigate 2.91 lakh hectares, generate 960 MW of power, and fulfil the water needs of industries and 540 villages in But bureaucratic wrangles between the Centre and the state have dealt heavy blows to the much-needed PIP, the officials say.

Though the project had been under contemplation since 1941, the works started in 2005. The efforts to complete it gained momentum in 2015, following the bifurcation of united Andhra Pradesh, says V Sridhar, of Irrigation Project.

According to him, 68.31 per cent of the works have been completed and the rest will be finished by December 2019.

He says Naidu conducted 87 virtual reviews and visited the 30 times in the last three years. He reviews the work every Monday, in keeping with his slogan "on Somavaram".

The Centre declared it a national project in 2014. Since then, Rs 11,210 crore has been spent on it. The Centre has reimbursed Rs 6,727 crore to the state government, he says.

At a rally in Rajahmundry on Monday, Modi said Naidu was using Polavaram like an to draw money from the Centre and was responsible for delays in the project.

Naidu hit back, saying the Centre was yet to reimburse Rs 4,500 crore the spent in spite of the financial crisis."The project is a defunct ATM," he said.

Earlier, Shah had alleged gross corruption in the construction of Andhra Pradesh's ultra-modern capital Amravati and the

Last year, the had shot off a letter to the asking it to reply to an RTI on "large-scale corruption and illegalities in the execution of the Polavaram project".

says "central agencies themselves are involved in the project. There's no chance of covering up corruption. Everything is in black and white".

One of the major roadblocks in the project is that a large number of the PIP-affected families have not been rehabilitated yet.

"Rs. 33,000 crore is needed for rehabilitation of 98,000 affected families. The dam cannot be complete unless the affected families are resettled," says.

The cost of resettling the affected villagers was calculated according to the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The has submitted the estimates to the Centre which is scrutinising them, the says.

Naidu had earlier said Andhra Pradesh may stop paying taxes to the Centre if it doesn't provide funds for the rehabilitation work.

"The rehabilitation work has been completed to a certain extent. As and when the Centre gives the money, we will complete the rest of it. The central government will have to give the money. It is our right and is mentioned in the Andhra Pradesh Reorganisation Act. Modi is not doing us any favours," he had said.

According to officials, the release of funds by the Centre doesn't match the pace of the work at the

They say the onus to rehabilitate the villagers is on the Centre, which had declared Polavaram a national project in 2014 and promised to bear the construction cost for the period starting from April 1, 2014.

The has been directing a lion's share of its resources to the project, so much so that it has left no money to spend on its other flagship schemes, according to D Umamaheswara Rao, who has rejected the charges of cost escalation.

According to the officials, the Union ordered to stop the work at the twice. First, it questioned the need for a cofferdam to build the main dam and on the second occasion, it sought to know why the state government changed a

Odisha, Telangana and have also opposed the project, fearing that it may submerge populated areas in these states.

Recently, the appealed to the to review the environmental impact assessment of the project as the clearance was obtained in 2005.

Earlier, Odisha had written to Modi to stop the project until pending issues are resolved.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Tue, April 02 2019. 18:20 IST