NTPC to operationalise 800 Mw at Odisha\'s Darlipalli power plant in FY19

NTPC to operationalise 800 Mw at Odisha's Darlipalli power plant in FY19

"The commissioning activities of 800 Mw are going on. The unit will be operational in the current financial year", said a senior NTPC official

Nirmalya Behera  |  Bhubaneswar 

NTPC
NTPC

Country’s largest thermal power producer Ltd plans to operationalise 800 Mw of its 1600 Mw (2x800) supercritical coal-based at in Odisha's in the current financial year.

“The commissioning activities of 800 Mw are going on. The unit will be operational in the current financial year”, said a senior official.

By September 2019, the full capacity of 1600 Mw is projected to start producing power. The total cost of the project is pegged at Rs 125 billion.will get 50 per cent power of the total capacity.

The power major will source from its Dulanga mine to meet the raw material requirements. For additional requirements, it will source from Mahanadi Coalfields Ltd (MCL), a 100 per cent subsidiary of the India Ltd (CIL). The project will consume eight million tonnes of coal annually.

Besides (800 Mw), West Bengal (423 Mw), Jharkhand (142 Mw), Sikkim (21 Mw) and Bihar (215 Mw) are beneficiary states of the upcoming project.

"The power purchase agreements (PPAs) with all the states are already in place", said the official.

NTPC presently has two projects running in the state- Talcher Thermal Power Station (460 MW) and Talcher Kaniha (3000 MW). It plans to phase out its 460 Mw plant of Talcher Thermal Power Station (TTPS) which has already completed 25 years.

TTPS was taken over by NTPC Ltd from State Electricity Board in 1995. The country's largest power producer also has plans to have a 1320 Mw (2x660Mw) supercritical plant at TTPS after the phasing out of the existing 460 Mw.

Recently, the Odisha government and NTPC have been at loggerheads over cancellation of PPAs. Faced with the prospect of a glut in thermal power supplies from 2020 onwards, the state government had written to the Union government to scrap PPA signed with NTPC projects which is due to start commercial operations.

First Published: Thu, November 29 2018. 19:33 IST