NMDC plant receives raw materials\, production by July 2019

NMDC plant receives raw materials, production by July 2019

Press Trust of India  |  Kolkata 

The NMDC Ltd's upcoming 3 million tonne greenfield Plant in Bastar, Chhattisgarh, on Monday successfully received raw material, a major step towards commencing production by July next year, the state owned said.

Plant received the first rake of imported coking coal and also commissioned its Wagon Tippler at the Raw Material Handling System (RMHS) thereby bringing the plant commissioning to its penultimate step, NMDC said in a statement.

The plant received 4106 tonnes of coal, a part of the first consignment of 80m000 tonnes of coal imported from and offloaded at last week.

Imported coking coal and indigenous coal is blended and charged into the blast furnace along with to produce

In all, 4 wagon tipplers, critical part of the Rs 1395 crore RMHS will be utilised to offload 12 million tonnes of incoming raw material - iron ore, coking coal, limestone - that would be required annually to produce 3 million tonnes of steel, NMDC (technical) N K Nanda said.

The plant management is now following up on meeting all Safety and environmental norms.

Recently, an accident at Bhilai steel had left several people dead and many injured.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Mon, November 26 2018. 20:00 IST