Godrej's alternate land suitable for bullet train: NHSRCL to HC

Press Trust of India  |  Mumbai 

The (NHSRCL) told the today that it has found an alternate land proposed by the Group suitable for acquisition for the project.

The conglomerate had on the last hearing told a division bench of Justices N H Patil and G S Kulkarni that it had suggested an alternate plot.

However, it came to light that the said plot was embroiled in a title dispute between the government and the group.

Following this, Godrej suggested a second alternate plot to the NHSRCL in Vikhroli for the project.

The corporation, in an affidavit submitted to the court today, said the site is suitable.

"We will examine the proposal in detail and have also sent a modified sketch for the petitioner's (Godrej) consideration," the affidavit said.

The high court asked the concerned to also verify the second proposal.

"It should not happen that even this land is embroiled in some legal dispute," Justice Patil said.

The court also noted that apart from such technical aspects pertaining to land availability, the NHSRCL will also have to consider several other aspects before taking the project forward.

"There are a lot of things to consider apart from such technical aspects...environmental rules and regulations...presence of mangroves. You (NHSRCL) will have to look into all of this before you start work for the project," Justice Patil said.

NHSRCL assured the court today that it would work this out amicably with Godrej and come up with a solution.

The bench has posted the matter for further hearing on September 3.

The conglomerate, in its petition, has sought a direction to authorities concerned to change the project's alignment so that it can get nearly 8.6 acres of land belonging to its infrastructure arm Godrej Construction out of the plan.

Of the total 508.17 km of rail track between and Ahmedabad, about 21 km is planned to be underground, as per the current alignment of the project.

One of the entry points to the underground tunnel falls on the land in the eastern suburb of Vikhroli.

The foundation stone for the project was laid by and his Japanese counterpart in September last year in

The country's first bullet train will run at a maximum speed of 350 km per hour, covering the stretch in under three hours from the usual seven.

The train will stop at 12 stations, out of which four will be in