Rohtang tunnel to be open for traffic by 2022

IANS  |  Manali 

Construction of Rohtang tunnel, one of the world's most challenging motorable projects at 3,000 metres above sea level and which will provide an all-season connectivity to the landlocked Valley from here in Himachal Pradesh, may be completed by 2020.

However, a geological surprise in the form of a rivulet that sprung up in 2012 during the tunnel digging is posing a challenge. Its torrential inflow is emerging into the tunnel.

"As per the current pace of work, most likely we will complete all civil engineering work by December 2019," an involved in the tunnel construction told IANS.

He said electrical and ventilation works were also in progress simultaneously. "In all probabilities, the tunnel will be made operational by May-June 2020."

The project is being built by the (BRO), a wing of the Defence Ministry, in collaboration with Afcons, a joint venture with

The Rs 1,495-crore tunnel's foundation stone was laid by (UPA) on June 28, 2010 in the picturesque near here.

sources said the tunnel had missed its February 2015 deadline owing to tough geographical conditions in the Himalayas along with harsh climatic conditions, besides a limited working season of six months in the tunnel's north portal.

Even the project is going to miss its second deadline 2019, admitted the

The tunnel, whose both ends can be accessed after negotiating 20 landslide and snow avalanche zones, is located at altitudes ranging above 3,000 metres and lies beneath the snow covered Rohtang Pass, whose 70 per cent of the top remains under snow even during summer.

But the delay of almost five years will face a cost overrun of Rs 2,000-2,500 crore.

Taming the glacial-fed Seri rivulet is still a challenge for the engineers.

It's a tributary of the and the tunnel alignment is crossing beneath the rivulet.

"Earlier, we were encountering the Seri rivulet's impact in 562 metre area. Now, we have managed to reduce its impact to just 30 metres. Very soon we will manage to control its entire flow and seepage inside the tunnel," said another

Situated in the Pir Panjal ranges, the highway tunnel will provide ample room for two-way traffic and is designed to cater to a maximum vehicular speed of 80 km per hour.

Upon completion, it will also be a boon for the cold deserts of Valley, where over 20,000 people remain cut off from the rest of the country in winter owing to the closure of the

Besides reducing road distance by approximately 46 km and saving of five hours between and Keylong, headquarters of Lahaul-Spiti, the tunnel has the capacity to ply 3,000 vehicles per day under any weather condition.

The completion of the is a key element in the Defence Ministry's attempts to make the entire 475 km-long Manali-Keylong-Leh highway, used by the armed forces to reach forward areas in Ladakh bordering and Pakistan, motorable round the year, said officials.

The strategic importance of the Manali-Leh link was realised by the almost a decade ago when tried to cut off the Srinagar-Leh road during the Kargil conflict, in a bid to restrict road access to Ladakh.

Currently, the movement of armed forces to the forward areas in Ladakh from side, which doesn't fall in the firing range of forces, is feasible only from June to mid-December.