May 25, 2018 5:38 pm

City of Regina gives green light to fill hole at Capital Pointe

On May 25, the City of Regina announced the green light has been given to fill the hole at Capital Pointe.

Derek Putz/Global News
A A

On May 25, the City of Regina announced the green light has been given to fill the hole at Capital Pointe.

Saskatchewan’s building and accessibility standards appeal board will still hear the appeal by Westgate developments, but won’t issue a “stay” on the order.

READ MORE: City tells appeal board Capital Pointe hole is “unsafe” amid calls for the site to be decommissioned

In the hearing last week, the board heard the developer hasn’t worked on the site since August, and an engineering company said while it is not “unsafe,” the work isn’t up to their standards.

Filling the hole won’t happen quickly. The City of Regina said it will take 17 weeks and 53,000 cubic meters of dirt to fill the 17-meter deep hole.

An appeal date has been set for June 18.