Federal officials running the country's multi-billion dollar shipbuilding program are refusing to say how badly off-track the schedule is for the delivery of new naval supply ships and the Canadian Coast Guard's planned heavy icebreaker — even though they've known since last fall.
A revised schedule has been presented to Public Services and Procurement Canada (PSPC) by executives at Seaspan, one of two go-to shipyards for the federal government.
There's a reference to the new schedule in an information paper, obtained by CBC News under the access to information law, which analyzes anticipated production gaps at the two shipyards.
When contacted, PSPC official Jean-Francois Letourneau recently confirmed the new schedule exists, but added the information in it is being withheld.
"The Government of Canada is currently reviewing (Seaspan's) Vancouver Shipyards' schedule and will communicate details once this review is complete," Letourneau said in an email.
Sliding deadlines
That review has been going on since last year, according to the documents.
The schedule is politically sensitive in light of the Liberal government's promise to fix the military procurement process — and because the delays speak to issues at the heart of the breach-of-trust case against Vice Admiral Mark Norman, the military's second-highest commander.
Last winter, Seaspan presented the Liberal government with a plan that could speed up the naval supply ship program, said a procurement source.
The government hasn't responded to the proposal, said the official, who asked not to be named because of the sensitivity of the file.
When the National Shipbuilding Strategy was launched in 2010, the navy was due to receive its supply ships this year.
A senior defence procurement official, in a recent interview with CBC News, said the new delivery date for the first vessel is now 2022.
"We're still four years away, give or take," said Pat Finn, a retired rear admiral who heads the equipment-buying section at National Defence.
"We're still negotiating some of those details, or should I say learning some of those details."
PSPC negotiates contracts on behalf of National Defence.
Delivery of the $1.3 billion polar icebreaker — the John G. Diefenbaker — had been tentatively set for 2021. It was bumped to 2023 in March of 2016, according to records tabled in Parliament.
Political embarrassment
The new date set out in Seaspan's recently revised schedule isn't public.
Ongoing procurement delays are proving to be a long-term source of political embarrassment for the Liberals.
Missed deadlines are at the heart of the alleged corruption case involving Vice-Admiral Norman, who was charged with one count of breach of trust in March.
He is accused of leaking cabinet secrets in relation to a contract for a leased navy supply ship — a vessel meant to fill the gap left by delays at Seaspan in building a permanent replacement.
An expert in defence procurement said the silence from the federal government about the state of the schedule is troubling, and appears calculated to avoid further political humiliation.
"We need to have an actual conversation about shipbuilding that is honest and provides an assessment of where we are so far," said Dave Perry of the Canadian Global Affairs Institute, who has authored several papers on the subject.
"It is well past time, in my opinion, for the Government of Canada, the current government, to live up to their very commendable pledges made by (then-minister of Public Services Judy Foote) two years ago to be more open and transparent."
Letourneau said information on the shipbuilding timetable will be made available in the coming months; in the meantime, he pointed CBC News at a 2016 annual report on shipbuilding and the department's website.
The opposition Conservatives asked for information last fall on delivery dates and were told in a written response that the schedule "is subject to commercial confidence restrictions and cannot be shared."
Official did not explain how a plan for a federally-funded program could be considered a "commercial" confidence.
"Failing to communicate has created a one-sided dialogue," said Perry. "There may be lots of reasons on why we are where we are, but what you can see as a member of the public is that all of the projects are clearly behind schedule."
Seaspan launched a coast guard research vessel — Sir John Franklin — in December of last year. It is still undergoing fitting and trials.
Comments
To encourage thoughtful and respectful conversations, first and last names will appear with each submission to CBC/Radio-Canada's online communities (except in children and youth-oriented communities). Pseudonyms will no longer be permitted.
By submitting a comment, you accept that CBC has the right to reproduce and publish that comment in whole or in part, in any manner CBC chooses. Please note that CBC does not endorse the opinions expressed in comments. Comments on this story are moderated according to our Submission Guidelines. Comments are welcome while open. We reserve the right to close comments at any time.