NTPC signs MoU with Government of Bihar; aims to improve performance of Power Sector in Bihar

Capital Market 

The MoU envisages transfer of (720 MW) to NTPC. In addition to this, State Power Generation Company's (BSPGCL) equities in (KBUN) & (Pvt.) Limited (NPGC) will also be transferred to NTPC.

Power from all the three power station shall be available to State of Bihar as before after approval by the Ministry of Power, Government of

Background:

NTPC, a Maharatna Company under Ministry of Power, Govt. of is the largest power generating company of with a total installed capacity of 53651 MW (including JVs) from coal, gas, hydro, solar and wind power projects. NTPC is on an accelerated growth trajectory to meet this long-term targets and currently has 21,071 MW capacity under construction. Company has two operational coal mines. NTPC in the past has demonstrated strong capability in turning around under-performing state owned power stations.

(720 MW) which is located at district in Bihar.

The Plant comprise of Stage-I (2x110 MW) (under advance stages of R&M) and Stage-II (2x250 MW) (under construction). NTPC with its expertise in construction of power projects and contract management capabilities is expected to complete the balance works and achieve sustained commercial operation of units in a time bound manner.

(Pvt) Limited is a 50:50 Joint Venture Company of and Bihar State (BSPGCL). The Company is developing a 1980 MW (3x660 MW) in district Aurangabad, Bihar. The project is currently under-construction.

(KBUNL) is a subsidiary company of in Joint Venture with Bihar State (BSPGCL). Currently NTPC and BSPGCL owns 72.64%and 27.36% equity holding in KBUNL respectively. KBUNL owns and operates (MTPS) (2x110 MW+ 2x195 MW) situated at Kanti, District Muzaffarpur in the State of Bihar. Plant is under operation.