Rlys, civic body review monsoon preparedness works in Mumbai

Press Trust of India  |  Mumbai 

Senior railway officials today said that pre-monsoon works, to ensure heavy rains don't stall train traffic in the metropolis and adjoining regions, had begun and a review was carried out by the and general managers of Western and Central Railways.

The work, officials said, involves the cleaning of drains and culverts that run beneath the rail tracks, removal of muck, trimming of branches of trees, surveying hilly areas for loose boulders and provision to drain out excess water from low-lying rail areas in case of heavy monsoon rains.

"The and GMs of and CR have reviewed monsoon preparedness works. The civic chief has promised all help to the railways to ensure that heavy monsoons do not disrupt train traffic," a senior civic official said today.

of CR, Sunil Udasi, said, "The preparatory work for monsoon started from February-March 2018. We have cleaned 79 culverts. An additional opening at has been provided to curb flooding in Kurla area."

He said that 25 spots within the jurisdiction of CR's Mumbai division had been identified for immediate attention.

"We have also requested the to provide pumps that have a water-draining capacity of 1,000 cubic metres per hour at Kurla and Mukhyaadhyapak nullah at Sion," he said.

He said that the had assured the railways that it would take action to ensure water from civic areas was not discharged onto railway territory, especially near Sandhurst Road station.

"The has also promised that it will get one building, deemed unsafe, at vacated before the arrival of the monsoon," Udasi said.

Ravinder Bhakar, in a statement, said that had met Ajoy Mehta and works like cleaning of storm water drains, clearing of dumped garbage, shifting of overhead pipelines and other issues were discussed.