Acquire land after sanction of works: Railway panel

PTI|
Mar 11, 2018, 12.41 PM IST
0Comments
Kolkata: Railway workers inspect an overhead railway electrical line after devot...
More than three-fifths of the total 349 delayed central projects belong to the railways, causing a cost overrun of Rs 1.73 lakh crore.
A railway panel has suggested that land for the national transporter's projects should be acquired only after sanction of works or before signing of construction contracts, to avoid delays in their completion.

According to a report of the statistics ministry submitted last month, more than three-fifths of the total 349 delayed central projects belong to the railways, causing a cost overrun of Rs 1.73 lakh crore.

"Delay in land acquisition and shifting of utilities are causing abnormal delay in commencing and completing the project. These two activities should be taken up and completed before finalising the contracts for actual execution of the work," the report said.

"These two should be taken up immediately after sanction of projects."

Under the present practice, construction contracts are processed without finalising drawing and plans, land acquisition and shifting of utilities like removal of trees, electrical poles etc., the report said.

The panel in its report on 'Improving Project Execution and Monitoring' has said while the completion periods are given as three to four years in the contract, in many cases it takes double the duration.

This, the panel said was adversely affecting the profit of contractors "leading to termination of many contracts and also arbitrations and litigations."

The report has said that General Managers should be delegated the powers for sanctioning part estimates and incurring expenditure for land acquisition and shifting of utilities to expedite the process.

The cost of the delay in railway projects can be estimated by the data provided in the statistics ministry report which monitored 350 projects of Indian Railways in October last year.

The total anticipated cost of the 213 delayed projects ballooned to Rs 2,96,496.70 crore from original cost of Rs 1,23,103.45 crore because of delays, it said, which is an overall cost escalation of 140.85 per cent.

The report of the rail panel was submitted to the Railway Board last month and is under consideration.
0Comments
Read more on

Also Read

The Latest: Lawmaker says North Korea sanctions working

Trump announces 'heaviest ever' sanctions on North Korea

India to invest in Iran in Rupees amid sanction fears

Trump threatens China with sanctions on trade imbalance

India seeks transparency in working of UN sanctions committees

Comments
Add Your Comments

From Around The Web

How to fix your Fatigue (do this every day)!

GundryMD

Send Money to India for $0 + Great Exchange Rates

Vianex

Arijit Singh Live in the U.S.-Book tickets now for 1+1 offer

Gaana Music Fest

5 Things You Never Knew Your Father's Last Name Could Tell..

Ancestry

More from The Economic Times

NHAI to rope in equity investors for roads

Lanka Prez heads to India amid tensions back home

How will Trump tariffs work? Will they likely succeed?

Chinese official warns against creeping Islamisation