359 infrastructure projects show cost overrun of Rs 2.05 lakh crore

PTI|
Mar 04, 2018, 01.49 PM IST
0Comments
359 infrastructure projects show cost overrun of Rs 2.05 lakh crore
Of these 1,289 projects in question, 359 reported cost overruns and 297 time escalation.
NEW DELHI: As many as 359 infrastructure projects, each worth Rs 150 crore and above, have shown cost overrun to the tune of Rs 2.05 lakh crore owing to delays and other reasons, a government report has said.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.

"Total original cost of implementation of the 1,289 projects was Rs 16,05,157.01 crore and their anticipated completion cost is likely to be Rs 18,10,733.70 crore, which reflects overall cost overruns of Rs 2,05,576.69 crore (12.8 per cent of original cost)," the ministry's latest flash report for November 2017 has stated.

Of these 1,289 projects in question, 359 reported cost overruns and 297 time escalation.

According to the report, expenditure incurred on these projects till November 2017 is Rs 6,45,872.52 crore, which is 35.67 per cent of the anticipated cost of the projects.

"Out of a total of 1,289 projects, 4 projects have reported completion and 10 new projects have been initiated on the monitor of this ministry during the current month. Of these, 15 projects are ahead of schedule, 312 are on schedule, 297 are delayed, 359 projects are showing cost overrun and 104 projects are showing both time and cost overrun with respect to original implementation schedules," the report said.

However, it said that the number of delayed projects has decreased to 258 if delay is calculated with reference to latest revised schedules of completion.

For 665 projects, where original/anticipated commissioning date has not been reported, all concerned have been requested by the ministry to provide the original /anticipated commissioning date so that these projects can be monitored for completion vis-avis the targeted dates.

It noted that out of 297 delayed projects, 51 projects have overall delay in the range of 1 to 12 months, 65 projects (13 to 24 months), 103 projects (25 to 60 months) and 78 projects (61 months and above).

The report attributes the time overrun to a host of issues, including delay in land acquisition, forest clearance, supply of equipment, funds constraints, Maoist incursion, legal cases and law and order situation.
0Comments
Read more on

Also Read

349 infrastructure projects show cost overrun of Rs 2 lakh crore

Delayed projects leading to cost overrun Rs 1.45L crore

213 railway projects report cost overrun of Rs 1.61 lakh crore

350 infrastructure projects show cost overrun of Rs 2.65 lakh crore: Government

350 infrastructure projects see cost overrun of Rs 1.95 lakh crore

Comments
Add Your Comments

From Around The Web

Desi TV Anywhere, Anytime and Affordable

SLING INTERNATIONAL

Send Money to India for $0 + Great Exchange Rates

Vianex

These actors have unbelievable bank balances.

Fropky.com

Parents are skipping meals to save their baby

Milaap

More from The Economic Times

Cops question Boney Kapoor, hotel staff and family

Sridevi's body taken to airport after embalming

Sridevi's mortal remains reach Mumbai, last rites at 3:30 pm

View: Fears of surveillance via Aadhaar are overblown