The construction work of a sewerage system in Rourkela, which is being undertaken by the L&T company, is absolutely horrible as residents across the town have been facing a lot of difficulties.
The contract for the construction work of the sewerage system of Rourkela city( west and east) was awarded to Waste Water Effluent Division of L&T by the Odisha Water Supply and Sewerage Board under the Housing and Urban Development Department, Government of Odisha in 2017.
The contract was worth Rs 340.20 crore. It also includes five years of operation and maintenance. It is a Government of Odisha initiative, but the Central Government is also giving some financial aid under the Atal Mission for Rejuvenation and Urban Transformation (Amrut) Yojana. As per the agreement, the sewerage system of Rourkela city in west will be done in Chhend, Civil Township, Udit Nagar, Basanti Colony, Tarkera and Nayabazar and in east Jagda, Koel Nagar, Shakti Nagar and Jhirpani. After the completion of the sewerage system work, the waste water of safety tank, kitchen and bathroom will go through the pipeline which is laid underground and thereafter will go to pumping station at different stations and then pumping will be done.
After pumping, the waste will go to transition manhole; then the waste water will go to main pumping station at Civil Township and thereafter will go to sewerage treatment plant at Balughat. The plant is scheduled to be completed by January 2020 and its capacity is 40 million liters per day.
The sewerage system work is presently going on at Chhend, Basanti Colony, Uditnagar, Civil Township and Tarkera while the work is yet to be started at other places of the city. Ever since the sewerage system work was started by the contractor, residents of the locality and the passersby have started facing a lot of problems and their woes have increased.
Basically, many accidents have been caused due to open manholes. House sewer connection has not yet been provided to the houses at a number of places even after four months of completion of pipe laying and manhole work. House sewer connection should have been provided during the pipe laying and manhole work.
The total work of pipe laying, manhole and house sewer connection which should be completed within 7-10 days by contractor, but it is taking months. The bitumen / concrete road which had been dug for sewerage connection work has not yet been restored and the public while going through these roads are falling in manholes. JCBs, while digging the road for sewerage system work, also are damaging water connection line following which water supply has been stopped to houses. The professional approach of the work is absolutely lacking by the contractor.
While admitting serious lapses occurring in the work by the contractor, Project Engineer of Odisha Water Supply and Sewerage Board Office of Rourkela, Karunakar Ghadei said, “ We have started monitoring the work and are working to address the grievances, so that public or residents would not face any problem.”