Scheduling committees meeting dates and decisions timeframes
Advisory Committee on Medicines Scheduling (ACMS) and Advisory Committee on Chemicals Scheduling (ACCS)
25 January 2018
Stakeholders should note that the following timetable outlines the anticipated administrative timeframes associated with matters referred by the delegates to an expert advisory committee meeting. As a result of consolidation of the Chemicals and Medicines scheduling functions into a single business unit, thus delivering a more efficient scheduling process, the lodgement deadlines for 2017 meetings are slightly earlier than in previous years. This timetable also reflects public consultation timeframes as required by legislation.
2017 meetings
March 2017 | July 2017 | November 2017 | |
---|---|---|---|
Scheduling Applications[1] | |||
Lodgement deadline[2] for scheduling applications. | 17 November 2016 | 6 April 2017 | 3 August 2017 |
Public notice[3] of proposed changes to scheduling and invitation to comment. | 22 December 2016 | 17 May 2017 | 6 September 2017 |
Public comment due | 10 February 2017 | 15 June 2017 | 6 October 2017 |
2017 ACCS, ACMS and joint ACCS/ACMS meeting dates | |||
The sequence of meetings is subject to the length of specific agenda(s) and may occur on any or all of the dates listed. | 21-23 March 2017 | 25-27 July 2017 | 21-23 November 2017 |
Anticipated timetable for delegate's decision-making | |||
Public notice of interim decisions[4] and invitation to comment. | 17 May 2017 | 15 September 2017 | 5 February 2018 |
Public comment due | 31 May 2017 | 3 October 2017 | 5 March 2018 |
Public notice of final decisions. | 29 June 2017 | 31 October 2017 | 10 April 2018 |
Effective date for Poison Standard (SUSMP) amendments | |||
Poison Standard (SUSMP) | 1 October 2017[5] | 1 February 2018 | 1 June 2018 |
Footnotes
- Scheduling Applications
Scheduling applications must be submitted using the Application to amend the Poisons Standard form approved by the Secretary. To be considered, applications must have sufficient information to support the proposal, and must meet the requirements outlined under section 52EAA of the Therapeutic Goods Act 1989. - Lodgement Deadline
To be considered within a scheduling cycle, an application must be submitted on or before the associated lodgement deadline. Any applications submitted after the lodgement deadline will be considered in the next scheduling cycle. - Public Notice - Pre-meeting Submissions on Scheduling Proposals
This public notice provides an opportunity for the public to comment on scheduling proposals that have been referred to an expert advisory committee. To submit a comment on a proposed scheduling amendment, use the Comment on a scheduling proposal coversheet. - Public Notice - Interim decisions
Only those that have provided a pre-meeting public comment are invited to submit a comment on an interim decision, by using the Comment on an interim decision coversheet. - Implementation date falls on a Sunday.
2018 meetings
March 2018 | July 2018 | November 2018 | |
---|---|---|---|
Scheduling Applications[1] | |||
Lodgement deadline[2] for scheduling applications. | 10 November 2017 | 2 March 2018 | 19 July 2018 |
Public notice[3] of proposed changes to scheduling and invitation to comment. | 21 December 2017 | 12 April 2018 | 30 August 2018 |
Public comment due. | 2 February 2018 | 10 May 2018 | 26 September 2018 |
2018 ACCS, ACMS and joint ACCS/ACMS meeting dates | |||
The sequence of meetings is subject to the length of specific agenda(s) and may occur on any or all of the dates listed. | 13-15 March 2018 | 26-28 June 2018 | 6-8 November 2018 |
Anticipated timetable for delegate's decision-making | |||
Public notice of interim decisions[4] and invitation to comment. | 7 June 2018 | 13 September 2018 | 7 February 2019 |
Public comment due | 5 July 2018 | 11 October 2018 | 7 March 2019 |
Public notice of final decisions. | 23 August 2018 | 29 November 2018 | 25 April 2019 |
Effective date for Poison Standard SUSMP amendments | |||
Poison Standard SUSMP effective date. | 1 October 2018 | 1 February 2019 | 1 June 2019[5] |
Footnotes
- Scheduling Applications
Scheduling applications must be submitted using the Application to amend the Poisons Standard form approved by the Secretary. To be considered, applications must have sufficient information to support the proposal, and must meet the requirements outlined under section 52EAA of the Therapeutic Goods Act 1989. - Lodgement Deadline
To be considered within a scheduling cycle, an application must be submitted on or before the associated lodgement deadline. Any applications submitted after the lodgement deadline will be considered in the next scheduling cycle. - Public Notice - Pre-meeting Submissions on Scheduling Proposals
This public notice provides an opportunity for the public to comment on scheduling proposals that have been referred to an expert advisory committee. To submit a comment on a proposed scheduling amendment, use the Comment on a scheduling proposal coversheet. - Public Notice - Interim decisions
Only those that have provided a pre-meeting public comment are invited to submit a comment on an interim decision, by using the Comment on an interim decision coversheet. - Implementation date falls on a Saturday