Excelsior Correspondent
JAMMU, Nov 1: To carry out the stringing work of 400 KV Double Circuit Dulhasti-Kishenpur Transmission Line, the shutdown of 33 KV Thathri to Gandoh Line, Thathri to Chowdary Power Project Line and 11 KV Thathri to Khara Line is being observed.
During the shut down, the power supply to Khara, Bunjwah, Jangalwar, Jakyas, Chillipingal, Gundoh, Bhatyas, Thathri, Changa and Saroor will remain affected on November 5 from 10 am to 3 pm.
Meanwhile, to carry out the work of laying of AB Cable to SMVD IME installation, the power supply to Panthal fed from 33 KV Jhajhar Kotli-Panthal Line will remain affected on November 2 from 7 am to 1 pm.