Work on road connecting mining leases to jetty to start from

Press Trust of India  |  Panaji 

The work on most awaited road connecting the mining leases to the jetties bypassing the thickly populated areas of South would begin from October this year.

The mining corridor project, which was mooted since last five years to avoid the trucks carrying iron ore, is expected to ease congestion on the main roads of South


State Infrastructure Development Corporation Chairman Dipak Pauskar told PTI that the tender for the mining corridor would be given next month.

He said the project which will be constructed in three phases would be completed in three years.

"Chief Minister has already given his go-ahead for the project. There are some issues related to the project as it runs through the forest areas. These issues are being sorted out," he said.

The first phase of the project is linking the mining villages of Uguem and Guddemol, having a stretch of around 8.9 km in Sanguem taluka, the second phase is between Guddemol and Capxem (8.4 km) and Cauvrem and Uguem (32 kms).

Pauskar saidGSIDC is going to fund the project, which will also include 10 per cent share from the district mineral funds, where themineowners have paid one-third of their royalty payment for the development of areas affected withminingactivities.

has mining as a major economic activity with the taluka of Sanguem having few of the important iron ore leases.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Thu, September 21 2017. 18:57 IST