GE bags power equipment supply contract from SPGroup in B'desh

Press Trust of India  |  Mumbai 

Energy solutions provider GE today said it has bagged a contract from the (SP) Group to supply the power generation equipment for the upcoming 220 MW combined cycle power plant in the Bhola district in

This 220 MW project will be GE's second power plant of the same capacity in Bhola while the first was commissioned in 2015, the company said in a statement issued here.


"Countries in South are accelerating towards achieving energy security which has led to greater investment in the sector. GE's technology advantage and local presence in South gives us an edge in addressing the needs of our customers in the region," GE's CEO of Gas Power Systems in South Deepesh Nanda said.

GE Power will supply the full suite of engineered equipment package (EEP) for the project, including two 6F.03 gas turbines, two heat recovery steam generators (HRSG), one steam turbine generator, condenser and associated control systems. GE will also provide technical expertise during the installation phase of the project.

Commenting on the development, SP Group Business Head - Power Business Mitesh Soni said, "This project will be an important milestone for the SP Group in Bangladesh, contributing towards increasing the country's power generation capacity".

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

First Published: Wed, September 13 2017. 18:42 IST