NTPC commissions 660 MW unit at Solapur project

Press Trust of India  |  New Delhi 

State-run power giant today said Unit-1 of 660 MW of Solapur Super Thermal Power Project in has been commissioned.

"With this, the commissioned capacity of Group has become 51,410 MW," the company said.



The has 20 coal-based, 7 gas-based, 10 solar PV, 1 Hydro, 1 wind and 9 Subsidiaries/Joint Venture power stations.

The company has capacity of over 20,000 MW under implementation at 23 locations across the country including 4,000 MW being undertaken by joint venture and subsidiary companies.

In FY'17, NTPC's annual generation exceeded 250 BUs. The company also commenced coal mining at Pakri Barwadih and commissioned first high efficiency 800 MW unit at Kudgi.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

NTPC commissions 660 MW unit at Solapur project

State-run power giant NTPC today said Unit-1 of 660 MW of Solapur Super Thermal Power Project in Maharashtra has been commissioned. "With this, the commissioned capacity of NTPC Group has become 51,410 MW," the company said. The NTPC has 20 coal-based, 7 gas-based, 10 solar PV, 1 Hydro, 1 wind and 9 Subsidiaries/Joint Venture power stations. The company has capacity of over 20,000 MW under implementation at 23 locations across the country including 4,000 MW being undertaken by joint venture and subsidiary companies. In FY'17, NTPC's annual generation exceeded 250 BUs. The company also commenced coal mining at Pakri Barwadih and commissioned first high efficiency 800 MW unit at Kudgi. State-run power giant today said Unit-1 of 660 MW of Solapur Super Thermal Power Project in has been commissioned.

"With this, the commissioned capacity of Group has become 51,410 MW," the company said.

The has 20 coal-based, 7 gas-based, 10 solar PV, 1 Hydro, 1 wind and 9 Subsidiaries/Joint Venture power stations.

The company has capacity of over 20,000 MW under implementation at 23 locations across the country including 4,000 MW being undertaken by joint venture and subsidiary companies.

In FY'17, NTPC's annual generation exceeded 250 BUs. The company also commenced coal mining at Pakri Barwadih and commissioned first high efficiency 800 MW unit at Kudgi.

(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)

image
Business Standard
177 22